Durham Chapel Hill Carrboro MPO, NC
Home MenuEast End Connector
The MPO participated in the development and design of the East End Connector, which will connect US 70 to NC 147 (Durham Freeway), thereby providing a limited-access highway connection between I-85 and I-40. As of fall 2014, the project is in right-of-way acquisition, is scheduled to be let (i.e., a construction contract awarded to a firm) in November 2014, and will likely start to be constructed in April 2015. The TIP identity number for this project is U-0071. An internet search of “east end connector” will provide additional sources of information. The project is sometimes referred to as the Triangle Connector.
For an update on the construction progress and schedule and for information on the development and design of the roadway, see the NCDOT Web page.
You can contact the NCDOT Division 5 office for detailed information on this project at (919) 220-4600.